ChallengeInstrumentation frequent failure, trappings
due to air line failure.Business ImpactProfitability.Solutions implemented after RCA and studyI took responsibility to set right Entire airline and associated like air filters etc converted to SS316 and atlas copco with MD 6 Dryer to avoid moisture in air line.OutcomeNo instrument failure thuse, loss prevented.
1988Â -Â 1988
Tata Chemicals, Mithapur
ChallengeDensh ash plant product failure remain
for 1 year.Business ImpactLoss of profit and loss of customer.Solutions implemented after RCA and studyI Was transferred to plant and shouldered accountability as head accountability, RCA done and corrected in 3 month time.OutcomeStable operation, regain customer improve profit.
1977 - 1990
Tata Chemicals, Mithapur.
ChallengeSoda ash manual operationBusiness ImpactProduction loss/profitability/more manpower.Solutions implemented after RCA and studyAutomation done- In house designed , valve manufactured, Flowmeter manufactured installed and automated control room established.OutcomeProduction increased 30 % better safety in operation. High profit.
1990 - 1992
Tata Chemicals, Mithapur.
ChallengeFrequent tripping of power plant (Blackout) every fortnight.Business ImpactLoss of profit and safety.Solutions implemented after RCA and studyI was transferred to Power plant as superintendent, change O&M practice, SOP based operation, spare, repair, coal selection, preventive maintenance, improved performance (one year no trip observed).OutcomeGreat improvement in profitability. Improve safety.
1990 - 1992
Tata Chemicals, Mithapur
ChallengeCoal fire boiler shutdown time reduced to 6 days from 21 days. Business ImpactLoss of profit.Solutions implemented after RCA and studyI was responsible for making power plant efficient and improve reliability.. Detailed planning, accountability, 24 hrs operation, skilled team, use of new tools, rewards, involve operation team, use hydro jets for cleaning. Replace instead repair on site.OutcomeBetter profitability.Â
1992 - 1994
Tata Chemicals, Mithapur
ChallengeFertilizer project expected to get delayed by two years at UP Babrala.Business ImpactGrass root Urea plant compressors 5 Units sets with entire accessory was in critical path. ( estimated delayed 2 years) loss of profit.Solutions implemented after RCA and studyTransferred to fertilizer plant and deputed to BHEL hyderabad and bought all items in time with great quality.OutcomeGreat impact on business bottom line.
1994 - 1994
Tata Chemicals, Mithapur
ChallengeFertilizer plant CPP and utility commissioning hold ups.Business ImpactBack from BHEL, GT HRSG, DM plant, bolers was not getting stabilise.Solutions implemented after RCA and studyWith in three month all units are stabilized with major changes made. It was nightmare, basic issue in design which was incorrected. 1- Boiler light ups, 2, naphtha supply to GT, GT hold ups due to FOG, HRSG logics, HRSG first stage flame, DM all valves wrong design.OutcomeTimely commissioning of Ammonia and urea plant.
1994 - 1994
Tata Chemicals, Mithapur
ChallengeBurn Instrumentation restoration after Boiler massive fire. Operation was hold.Business ImpactLoss in Profitability.Solutions implemented after RCA and studyI was back to mithapur in 1995 as head C&I- inhouse 4 boilers, 4 Turbine and generators instruments and plans was burns to ash, inhouse departmentally lead design, procurement, installation, commissioning and stabilisation in 5 month time. OutcomeEstimated time was two years by external agency. Back to normal in 5 m0nths.
2001 - 2002
Tata Chemicals, Mithapur
ChallengeEnergy loss due to improper operation of this turbine and Compressor anti surge.Business ImpactFertilizer UP. Loss in profitability.Solutions implemented after RCA and studyI was transferred as HOD electrical and instrumentation, worked on IGV control mode on auto as well s redefine surge line on COR compressors. This saved energy - 20 Cr/year. Outcomeimprovement in profitability.
2001 - 2002
Tata Chemicals, Mithapur
ChallengeTurn around time and startup was a challenge. Business ImpactTata chemicals - fertilizer UP. Loss in profitability.Solutions implemented after RCA and studyNew SOP for Turnaround made with no over maintenance, only identified valves and transmitter to be service. OutcomeSmooth start and stabilisation, better profitability.
2003 - 2005
Tata Chemicals, Mithapur
ChallengePoor safety management system and compliances.Business ImpactHigh accidents rate, fatal accidents.Solutions implemented after RCA and studyI was transferred back from Babarala, Safety culture through BSC- 5 Star processes as well due pond safety management introduce, I was owning section 2 which is implementation and achieved 5 star. OutcomeSafety standard has gone high.
2003 - 2005
Tata Chemicals, Mithapur
ChallengeCompany has made loss- ( import and new plants expansion by competitors)
Business ImpactProfitability eroded.
Solutions implemented after RCA and studyMckinsey service was hired- Iwas leading energy cost reduction where structured process of cost effectiveness was implemented and thus company came back on track.
OutcomeProfitability has gone high.
2003 - 2005
Tata Chemicals, Mithapur
ChallengePF and CFBC boilers was not reliable, frequent failure and availability was less than 70 %. Business ImpactProfitability eroded. Plant upset created safety hazards.Solutions implemented after RCA and studyI was back to mithapur as head power plant and started working on PF and CFBC boilers, all set right through RCA, combustion chemistry was challenged and set right with SOP of buying coal and using, Boiler availability is 100 % from 65 % since 2005 till date. For cost reduction petcoke use started in CFBC and have cost reduction in unit cost by 50 %. OutcomeGreat Stability, cost reduction, safety, profitability.
2005 - 2008
Essar Power-VPCL
ChallengePhase 1 CPP for refinery ( Essar Oil limited- EOL.)Business ImpactRefinery commissioning - ( EOL). Solutions implemented after RCA and studyOld uninstalled oil and Gas 77 MW + 230 tons of steam plant was in bad situation due to remain at sea cost for long time, challenges was divided in to small and focus approach, solution reached and worked very hard with team. ( challenges - IBR,Documents, details, etc) OutcomeRefinery was commissioned in time.
2008 - 2012
Essar Power-VPCL
ChallengeProject execution from conceptualization to commissioning. Business Impactdelay/ poor performance loss of profitability as well as safety. Solutions implemented after RCA and studyPhase 2 I was healing construction , and decision makers for selection of equipment, better quality standard and QAP with QC an force, Format process for commissioning, coal storage and management, fire protection and detection, safety and fire management, people trained.
OutcomeTimely commissioning of coal based power plant started giving return better then estimated as Gas cost was doubled by this time.
2008 - 2012
Essar Power- VPCL
ChallengeCoal based can not work for refinery energy supply.
Business Impact1 $ to 1.5 $ per barrel process. 20 MMTPA refinery.
Solutions implemented after RCA and studyDesign,Technology, selection of equipments, procurement, construction, commissioning was done keeping in mind reliability.
Outcome2 billion $ straight bottom line in 10 years
2012-2023 (17500) Rs Cr.
2018
Essar Power-VPCL
ChallengeSea water cooling towers cells collapse and on inspection found many more can. Business ImpactRefinery to cut down production so huge loss on through puts.Solutions implemented after RCA and studyRCA indicated Poor preservation and maintenance done.. However to get immediate solution interconnection was established during shutdown
OutcomeSaved disaster to stop refinery/ reduce output.
2010 - 2018
Essar Power- VPCL
ChallengeSea water intake line from pump house to refinery is 17 KM leaks frequently.
Business ImpactFrequent shutdown create unrest in villages , water shortage for cooling, time pressure.
Solutions implemented after RCA and studyRCA- frequent start stop gives water hammering to GRP line so joints get weak and leak.- actions SOP for start and stop pumps.
OutcomeNo leaks since 4 years
2008 - 2012
Essar Oil-EOL
ChallengeCooling tower cells colleps and most of weak
Business ImpactBusiness disturbance. Solutions implemented after RCA and studyInterconnection provided to meet business continuity.OutcomeOperation continue.
2018
Essar Nayara Energy
ChallengeStorm Water - pollution
Business ImpactEnvironment non compliance.
Solutions implemented after RCA and studySpecific area water collected in pond large pond and saved contamination of entire storm water stream.
OutcomeSaved Business closure.
Previous
Next
Streamline your processes and boost profitability. Call us for a personalized solution.
ChallengeInstrumentation frequent failure, trappings
due to air line failure.Business ImpactProfitability.Solutions implemented after RCA and studyI took responsibility to set right Entire airline and
associated like air filters etc converted to SS316 and
atlas copco with MD 6 Dryer to avoid moisture in air line.OutcomeNo instrument failure thuse, loss preventes.
ChallengeInstrumentation frequent failure, trappings
due to air line failure.Business ImpactProfitability.Solutions implemented after RCA and studyI took responsibility to set right Entire airline and
associated like air filters etc converted to SS316 and
atlas copco with MD 6 Dryer to avoid moisture in air line.OutcomeNo instrument failure thuse, loss preventes.
ChallengeInstrumentation frequent failure, trappings
due to air line failure.Business ImpactProfitability.Solutions implemented after RCA and studyI took responsibility to set right Entire airline and
associated like air filters etc converted to SS316 and
atlas copco with MD 6 Dryer to avoid moisture in air line.OutcomeNo instrument failure thuse, loss preventes.
ChallengeInstrumentation frequent failure, trappings
due to air line failure.Business ImpactProfitability.Solutions implemented after RCA and studyI took responsibility to set right Entire airline and
associated like air filters etc converted to SS316 and
atlas copco with MD 6 Dryer to avoid moisture in air line.OutcomeNo instrument failure thuse, loss preventes.